Flow
Cycle time, time per status, throughput and forecast.
Completed Tickets
420
Median Cycle Time
💡
12 j
P85 : 22 j
Work In Progress
💡
20
Story Points
1819 SP
Actual / Planned
105%
Time Spent per Status
Average time spent in each status (working days)
💡 How to read this chart?↓
Lines show the cumulative elapsed time as tickets progress through each pipeline stage — each point is the total time spent from the start of the pipeline up to and including that status.
Hover over any status to see the average time spent exclusively in that stage (in working days).
Cohort: only completed ("Done") tickets {period}are counted. This ensures data is not skewed by tickets stuck in progress.
GOOG
AAPL
MSFT
Moyenne
Aging WIP
Age of each in-progress ticket (working days since work started)
💡 How to read this chart?↓
- Each dot is an in-progress ticket — the higher, the older.
- Dashed lines: P50 / P85 of the historical cycle time. A ticket above the P85 line is already taking longer than 85% of past tickets.
- Tickets above P85 are your first candidates for the daily standup.
GOOG
AAPL
MSFT
Weekly Throughput
Tickets completed per week, by brand
GOOG
AAPL
MSFT
🎲 Monte Carlo Forecast
based on the last 26 weeks of throughputHorizon
Likely (85%)
Median (50%)
2 weeks
≥ 12
≥ 15
4 weeks
≥ 26
≥ 31
8 weeks
≥ 55
≥ 63
Planned vs Actual (Dev)
Estimated Story Points vs actual development Man-days
💡 How to read this chart?↓
This chart compares estimates with actual time spent.
- Hatched bars: planned Story Points (initial estimate)
- Solid bars: actual development Man-days
- Exclusion: tickets without Man-days (= 0) are ignored.
GOOG - Planned
GOOG - Actual
AAPL - Planned
AAPL - Actual
MSFT - Planned
MSFT - Actual